Public plaza renovation / San Antonio, Texas
San Antonio Main Plaza renovations
The lighting legend points to a fixture schedule. The sheet has none.
The Main Plaza project renews a public plaza in downtown San Antonio. It includes many light fixture types and a rooftop heating and cooling unit. Our review found two places where the drawings leave a bidder without one clear answer.
Finding 01
The lighting legend sends bidders to a fixture schedule that is missing.
Sheet LD101 is titled "Enlarged Lighting Layouts and Fixture Schedule". Its legend says "See fixture schedule on sheet LD101 for full specifications." The sheet shows the restroom building plan, the vault level plan and the legend. It shows no fixture schedule.
Legend note
See LD101Points to a fixture schedule
Sheet LD101
No scheduleTwo plans and a legend only
Why it matters
The legend lists fixture types from F1A to XF11, including pole lights, string lights and an RGBW floodlight. Without the schedule, a bidder has no manufacturer, catalog number or wattage to price.
The question to ask
Sheet LD101 directs bidders to a fixture schedule on LD101, and none appears there. Please issue the complete luminaire schedule with manufacturer, catalog number, wattage, voltage and mounting for each type.
See the actual drawing excerpts
LD101, sheet 154 of 220, title block and legend. Source report finding 1.


What we know now: As of October 25, 2026, no addendum or bidder question addressed the lighting schedule.
Finding 02
The rooftop unit has different electrical data on two sheets.
The M502 rooftop unit schedule lists RTU-1 with a 5 HP fan motor at 208/3, MCA 74.0 and MOCP 80.0. The E600 equipment connection schedule lists RTU-1 at 3 HP, 51.2 A full load, 64.0 A MCA and 70.0 A MOCP.
Mechanical schedule
5 HP, MCA 74.0M502, RTU-1
Electrical schedule
3 HP, MCA 64.0 AE600, RTU-1
Why it matters
The mechanical and electrical trades could price different units. The wire and breaker size follow whichever data governs. The numbers alone do not show a code problem.
The question to ask
M502 lists RTU-1 at 5 HP, MCA 74.0 and MOCP 80.0. E600 lists it at 3 HP, MCA 64.0 A and MOCP 70.0 A. Please confirm the governing RTU-1 electrical data and update the electrical design to match.
See the actual drawing excerpts
M502, rooftop unit schedule; E600, equipment connection schedule. Source report finding 2.


What we know now: As of October 25, 2026, no addendum or bidder question addressed the RTU-1 data.
Document status
These findings describe the documents checked on October 25, 2026. We have no confirmed project-team answer or cost saving. The next step is a question to the designer before bids are priced.
These examples are questions for the project team to check. They are not a design approval or a complete review of the project. Bidders should send questions only through the owner’s official question process.
See an error? Email contact@mebbian.ai and we will correct the page.
Questions about this review
Are there drawing conflicts in the San Antonio Main Plaza Renovations bid set?
Mebbian's reviewer-led check found a lighting legend on LD101 that points to a fixture schedule the sheet does not show. It also found RTU-1 listed at 5 HP on M502 and 3 HP on E600. These findings describe the documents checked on October 25, 2026.
How do you check a lighting legend against the fixture schedule?
Follow each legend note to the sheet it names and confirm the schedule is there. Mebbian's reviewer-led check found the LD101 legend points to a schedule on LD101 that does not appear. These findings describe the documents checked on October 25, 2026.
Source documents
Check the original documents.
Project listed as: City of San Antonio Main Plaza Renovations, RFCSP 2026-118
Bid drawings for RFCSP 2026-118, including LD101, M502 and E600, and the project manual.
City of San Antonio bid documents on CivCast ↗
Search for Main Plaza Renovations or RFCSP 2026-118. A CivCast account may be needed to open the documents. Later changes may resolve a finding. Use the latest documents for any bid or design decision.